Holywood MEI
Multi Element Improvements to 33
NIHE Dwellings in the Strand Avenue Area of Belfast.
- 14no dwellings at 18, 20, & 22 Strand Avenue - works
began 5th February 2007 with anticipated completion 23rd July
2007.
- 8no dwellings at block 24 plus house no 28 and
32. Works to begin 23rd July 2007 with anticipated
completion 5th November 2007.
- 5no dwellings and 2
no sold dwelling at block 10 plus house no 12. Works to
begin 5th November 2007 with anticipated completion 29th
February 2007.
- External works to take place from 29th
February 2007 to 30th March 2007.
|